An aerial view of a residential street lined with trees, houses, and construction equipment working on the road.

Two of the three water main replacement projects are currently underway. The S. Depew St. project is now complete. The new water main has been installed, placed into service, and final paving is finished.

S. Depew St. project

Levi Contractors are actively excavating and installing new PVC pipe in the Columbine Hills neighborhood. Project details are provided below.

W. Chestnut Ave. – This project will replace 1,453 feet of 6″ cast iron pipe with 6″ PVC pipe in W. Chestnut Ave. from S. Lamar Court to S. Kendall Blvd.  subdivision.

W. Chestnut Ave. from S. Lamar Court to S. Kendall Blvd

S. Jay Dr. – This project will replace 623 feet of 12″ cast iron pipe with 12″ PVC pipe in S. Jay Dr. from W. Elmhurst Dr. to W. Alder Ave.

S. Jay Dr. from W. Elmhurst Dr. to W. Alder Ave
A street excavation in progress with workers, heavy machinery, and a blue pipe being installed.