Skip to main content

Water Main Replacement in Leawood

The image shows a residential neighborhood map with street names and Leawood Elementary School marked nearby.

Posted on June 29, 2026 

The six water main replacements listed below are scheduled for construction this summer in the Leawood subdivision. The construction contract was awarded to Diaz Construction. Work is expected to begin in July and completed this fall, weather permitting.

The district intends to keep the community informed about the projects to help minimize disruptions and ensure everyone is prepared for any temporary inconveniences during construction. The anticipated working hours are Monday through Friday, 7:00 am – 5:00 pm. Affected residents will receive written notification from the contractor closer to the start date of construction.

District staff, its consultant, and its construction contractor will work closely with the residents and regulatory agencies to minimize disruptions to traffic and the environment. Water service may be interrupted when the new water mains are connected to the existing mains, however, this will be limited to a few hours at a time. Residents will be notified at least 24 hours in advance before service is interrupted. Emergency shutoffs may occur due to unforeseen circumstances. If requested, the district can supply bottled drinking water to impacted customers during scheduled outages.

If you have further questions concerning this project, need additional information, or would like to request bottled drinking water during scheduled outages, please contact the district office at 303-979-2333 or info@plattecanyonwsd.gov.

2026 Water Main Replacement Projects

S. Lamar Dr. – This project will replace 1,013 feet of 6″cast iron pipe with 6″ PVC pipe in S. Lamar Dr. from W. Leawood Dr. to S. Marshall Ct.

W. Burgandy Dr. – This project will replace 857 feet of 6″ cast iron pipe with 6″ PVC pipe in the W. Burgandy Dr. loop of W. Brittany Pl.

S. Marshall Dr. – This project will replace 1,931 feet of 8″ cast iron pipe with 8″ PVC pipe in S. Marshall Dr. from W. Leawood Dr. to S. Marshall Ct.

S. Newland St. – This project will replace 347 feet of 6″ cast iron pipe with 6″ PVC pipe in the S. Newland St. cul-de-sac of W. Leawood Dr.

S. Otis Ct. – This project will replace 284 feet of 6″ cast iron pipe with 6″ PVC pipe in S. Otis Court.

S. Nixon Ct. – This project will replace 280 feet of 6″ cast iron pipe with 6″ PVC pipe in S. Nixon Court.

 

Join our mailing list